Large Dams and Water Management

Watershed area studies and water resources assessment and development are carried out by SAKOO to determine and to implement the utilization of the water resources in river basins. These studies frequently involve multi-purpose development and include: Dams and reservoirs, Watershed management; Flood planning and control; River management and water quality; Hydroelectric power generation; and Erosion control. Our work and experience covers nearly all aspects of water cycle from management and control of water resources to the final transmission to the end user.


• East Azarbaijan(Iran) Regional Water Authority

• Regional Water Authority

• Fars Regional Water Authority

• Hormozgan Regional Water Authority

• Iran Water and Power Development Co. (IWPC)

• Kohgiluyeh and Boyer-Ahmad Regional Water Authority

• Mazandaran Regional Water Authority

• West Azarbaijan (Iran) Regional Water Authority

• Yazd Regional Water Authority

Rudbar Lorestan

Location: Rudbar Lorestan Dam & Hydropower Plant Project is located on Rudbar river ( in upper east of Dez river catchment area) in Zagros mountain, and nearly 100 Kilometers distance from south of Aligoudarz city in Lorestan province.

Project Objectives: The main objectives of the project can be summarized as follows:
• Hydro power generation of 986 GWH/ year by using an installed capacity of 450 MW (2 Units)
• Reducing depreciation expenses of thermal power plants
• Job creating in region during project construction and operation period
• Creation of Recreational and tourism areas

Company annual reports that contain important financial information

Project Features:
Dam Type: Earthcore Rockfill Dam (ECRD)- inclined Clay Core
Body Volume:4.45 m3
Spillways Type: Free tunnel spillway
Powerhouse Type: Ground/Surface
Installed Capacity: 450 MW (2 units)



Siah Bishe

Location: Siah Bishe Pumped Storage Power Plant Project is located in the vicinity of Siah Bishe in Mazandaran Province, 125 km to the north of Tehran and 10 km to the north of Kandovan Tunnel along Chalus River. The project takes its name from the nearby village of Siah Bishe.

Project Objectives: The main objectives of the project can be summarized as follows:
• Creation of balance in the national electricity network during peak hours and non-peak hours
• Generation of hydro power energy during high- load consumption hours with a capacity of 1040 MW
• Consumption of electricity energy during low- load consumption hours with a capacity of 960 MW
• Reduction of depreciation costs of thermal power plants up to 19 million dollars per year
• Creation of Recreational and tourism areas for holidays
• Job creating in region during project construction and operation period

Company annual reports that contain important financial information

Project Features Of Upper & Lower Dam:
Dam Type: Both, Concrete Faced Rock Fill Dam (CFRD)
Body Volume: Upper Dam:1.5 Million m3
Lower Dam: 2.4 Million m3
Spillways Type: Both, Free Staircase
Powerhouse Type: Underground-Cavern
Installed Capacity: 1040 MW (4 units of 260 MW)



Tang-e-Sorkh

Location: Tang Sorkh Project is located on Maaliabad river in Fars province, 3 km to the south west of Shahid Beheshti residential area in north west of Shiraz.

Project Objectives: The main objectives of the project can be summarized as follows:
• Storage of seasonal river flows of Maaliabad river, adjusting it for environmental needs and maintaining river flow.
• Flood control regarding to Dam location in upstream of Shiraz
• Job creating in region during project construction and operation period

Company annual reports that contain important financial information

Project Features:
Dam Type: Earthcore Rockfill Dam
Body Volume: 1.9 mcm
Spillways Type: Free Ogee spillway





Gelevard Reservoir Dam

Location:Gelevard Reservoir Dam is located on Neka river, Zarandin Road, 45 km from south-east of Neka city in Mazandaran Province.

Project Objectives: The main objectives of the project can be summarized as follows:
• Storage and regulation of water for irrigating agricultural lands
• Urban Water Supply
• Flood Control

Company annual reports that contain important financial information

Project Features:
Dam Type: Concrete Faced Rock Fill Dam (CFRD)
Body Volume : 2.3 Million m3
Spillways Type : Ogee spillway





Shiv Dam

Location: Shiv Project is located on Shiv river in Fars and Kohgiluyeh and Boyer-Ahmad provinces.

Project Objectives: The main objectives of the project can be summarized as follows:
• Supplying drinking and industrial water
• Supplying agricultural water of Kenareh, Lirab, …

Project Features Of Upper & Lower Dam:
Dam Type: Earthfill Dam with Clay Core
Body Volume : 5.0 M3
Spillways Type: Free ogee